PUBLIC LAW 104-201—SEPT. 23, 1996
110 STAT. 2781
(B) for the Air Force Reserve, $52,805,000.
SEC. 2602. AUTHOMZATION AND FUNDING FOR CONSTRUCTION AND
IMPROVEMENT OF NAVAL RESERVE CENTERS.
(a) ARMY RESERVE CENTERS.— Using amounts appropriated
under the heading "MILITARY CONSTRUCTION, NAVAL RESERVE" in
the Military Construction Appropriations Act, 1995 (Public Law
103-307; 108 Stat. 1661), for the construction of a Naval Reserve
Center in Seattle, Washington, the Secretary of the Army may
carry out a military construction project for the construction of
an Army Reserve Center at Fort Lawton, Washington, in the total
amount of $5,200,000, of which $700,000 may be used for program
and design activities relating to such construction.
(b) NAVAL RESERVE FACILITIES. — Using amounts appropriated
under the heading "MILITARY CONSTRUCTION, NAVAL RESERVE" in
the Military Construction Appropriations Act, 1995 (Public Law
103-307; 108 Stat. 1661), for the construction of a Naval Reserve
Center in Seattle, Washington, the Secretary of the Navy may
carry out—
(1) a military construction project for the construction of
an addition to the Naval Reserve Center in Tacoma, Washington, in the total amount of $4,200,000;
(2) unspecified minor construction at Naval Reserve facilities in the total amount of $500,000; and
(3) planning and design activities with respect to improvements at Naval Reserve facilities in the total amount of
$500,000.
SEC. 2603. UPGRADE AIR NATIONAL GUARD FACILITIES, BANGOR
INTERNATIONAL AIRPORT, MAINE.
(a) PROJECT AUTHORIZED. —Using amounts appropriated pursuant to the authorization of appropriations in section 2601(3)(A)
and amounts appropriated pursuant to authorizations of appropriations enacted after the date of the enactment of this Act, the
Secretary of the Air Force may carry out a construction project
to upgrade Air National Guard base and support facilities at Bangor
International Airport, Maine. The Secretary may contract for
architectural and engineering services and construction design services in connection with the construction project.
(b) LIMITATION ON TOTAL COST OF PROJECT. —The total cost
of the construction project authorized by subsection (a) may not
exceed $13,000,000.
(c) FISCAL YEAR 1997 FUNDING. —Of the amount authorized
to be appropriated in section 2601(3)(A), $7,000,000 shall be available to carry out the construction project authorized by subsection
(a).
TITLE XXVII—EXPIRATION AND
EXTENSION OF AUTHORIZATIONS
Sec. 2701. Expiration of authorizations and amounts required to be specified by
law.
Sec. 2702. Extension of authorizations of certain fiscal year 1994 projects.
Sec. 2703. Extension of authorizations of certain fiscal year 1993 projects.
Sec. 2704. Extension of authorizations of certain fiscal year 1992 projects.
Sec. 2705. Effective date.
�