[86 STAT. 835]
PUBLIC LAW 92-000—MMMM. DD, 1972
[86 STAT. 835]

86 STAT. ]

PUBLIC LAW 92-500-OCT. 18, 1972

thereof (as approved by the Administrator). Any grant (other than for reimbursement) made prior to the date of enactment of the Federal Water Pollution Control Act Amendments of 1972 from any funds authorized for any fiscal year beginning after June 30, 1971, shall, upon the request of the applicant, be increased to the applicable percentage under this section. "(b) The amount of the grant for any project approved by the Administrator after January 1, 1971, and before July 1, 1971, for the construction of treatment works, the actual erection, building or acquisition of which was not commenced prior to July 1, 1971, shall, upon the request of the applicant, be increased to the applicable percentage under subsection (a) of this section for grants for treatment works from funds for fiscal years beginning after June 30, 1971, with respect to the cost of such actual erection, building, or acquisition. Such increased amount shall be paid from any funds allocated to the State in which the treatment works is located without regard to the fiscal year for which such funds were authorized. Such increased amount shall be paid for such project only if— " (1) a sewage collection system that is a part of the same total waste treatment system as the treatment works for which such grant was approved is under construction or is to be constructed for use in conjunction with such treatment works, and if the cost of such sewage collection system exceeds the cost of such treatment works, and "(2) the State water pollution control agency or other appropriate State authority certifies that the quantity of availaljle ground water will be insufficient, inadequate, or unsuitable for public use, including the ecological preservation and recreational use of surface water bodies, unless effluents from publicly-owned treatment works after adequate treatment are returned to the ground water consistent with acceptable technological standards.

835

Ante, p. si6.

"PLANS, SPECIFICATIONS, ESTIMATES, AND PAYMENTS

"SEC. 203. (a) Each applicant for a grant shall submit to the Administrator for his approval, plans, specifications, and estimates for each proposed project for the construction of treatment works for which a grant is applied for under section 201(g)(1) from funds allotted to the State under section 205 and which otherwise meets the requirements of this Act. The Administrator shall act upon such plans, specifications, and estimates as soon as practicable after the same have been submitted, and his approval of any such plans, specifications, and estimates shall be deemed a contractual obligation of the United States for the payment of its proportional contribution to such project. "(b) The Administrator shall, from time to time as the work progresses, make payments to the recipient of a grant for costs of construction incurred on a project. These payments shall at no time exceed the Federal share of the cost of construction incurred to the date of the voucher covering such payment plus the Federal share of the value of the materials which have been stockpiled in the vicinity of such construction in conformity to plans and specifications for the project. "(c) After completion of a project and approval of the final voucher by the Administrator, he shall pay out of the appropriate sums the unpaid balance of the Federal share payable on account of such project. "LIMITATIONS AND CONDITIONS

"SEC. 204. (a) Before approving grants for any project for any treatment works under section 201(g)(1) the Administrator shall determine—

.

Limitation,