GENERAL CALENDAR OF EVENTS
August 12, 1913 Clarke County, Washington voted bonds for construction.
November 4, 1913 Multnomah County, Oregon, voted bonds for construction.
Novomber 29, 1913 The Columbia River Interstate Bridge Commission organized.
December 29, 1913 Commission selected Engineers.
December 29, 1913 Commission directed Engineers to prepare preliminary plans and to make a report recommending a location for bridge and approaches.
January 31, 1914 Bill authorizing construction passed Congress.
March 26, 1914 Engineers completed preliminary studies, and recommended location of structure.
March 30, 1914 Commission adopted report and located structure.
April 13, 1914 Engineers made application to Secretary of War for permit for construction.
April 20, 1914 Public hearing of War Department to consider proposed plans.
June 12, 1914 Tentative approval of plans given by Secretary of War.

Progress delayed by financial disturbance due to commencement of war in Europe.

November 1914 Clarke County sold $250,000 bridge bonds.
November 9, 1914 Multnomah County sold $250,000 bridge bonds.
December 1914 Clarke County sold $250,000 bridge bonds.
December 14, 1914 Multnomah County sold $1,000,000 bridge bonds.