South Yorkshire Light Rail Transit Act 1989

The paged version of this document contained the following header content in the margin: Part IVcont

(3) In the exercise of the powers of section 12 (Temporary stoppage of highways) of the Act of 1988 as applying for the purposes of this Act the Executive shall at all times provide reasonable access, with or without vehicles, plant, machinery and materials, to the railways board's Woodbourn Road depot and to any other station or depot of the railways board or other railway property:

(4) The Executive shall, before commencing the construction of the specified works supply to the railways board proper and sufficient plans thereof for the approval of the engineer and shall not commence the construction of those works until such plans have been approved in writing by the engineer or settled by arbitration: Provided that approval of plans supplied under this paragraph shall not be unreasonably withheld and, if within 56 days after the plans have been supplied to the railways board the engineer shall not have intimated his disapproval of the plans and the grounds of his disapproval, he shall be deemed to have approved them:

(5) If within 56 days after such plans have been supplied to the railways board, the railways board give notice to the Executive that the railways board desire themselves to construct any part of the specified works which, in the opinion of the engineer, will or may affect the stability of any operational railway or the safe operation of traffic on the railways of the railways board then, if the Executive desire such part of the specified works to be constructed, the railways board shall construct the same with all reasonable dispatch on behalf of. and to the reasonable satisfaction of, the Executive in accordance with the plans approved or deemed to be approved or settled as aforesaid:

(6) Upon signifying his approval or disapproval of the plans the engineer may specify any protective works (whether temporary or permanent) which in his opinion should be carried out before commencement of the construction of the specified works to ensure the safety or stability of the railways of the railways board, and such protective works as may be reasonably necessary for those purposes shall be constructed by the railways board or by the Executive, if the railways board so desire, with all reasonable dispatch, and the Executive shall not commence the construction of the specified works until the engineer shall have notified them that the protective works have been completed to his reasonable satisfaction:

(7)(a) The Executive shall give to the railways board notice in writing of their intention to commence the construction of any of the specified works in accordance with sub-paragraph (b) below and, except in case of emergency (when they shall give such notice as may be reasonably practicable), of their intention to carry out any works for the repair or maintenance of the specified works in so far as such works of repair or maintenance affect or interfere with railway property:

(b) The period of notice required under sub-paragraph (a) above shall be—

(i) 6 months in any case where the engineer, upon signifying his approval or disapproval of plans supplied to the railways board under paragraph (4) above, has reasonably given his opinion that the construction or maintenance of the specified works will require the Executive to have temporary occupation of the permanent way of any operational railway (including land lying within a distance